Caxton House (1) Westminster This Cat B 6 week project was to create a new reception area and new main entrance at DWP HQ in Westminster.

  • Scope of works included:

  • Soft strip-out of ground floor area to create new controlled access main entrance, reception area and controlled entry point in to the building

  • Removal of existing interior inlcuding reception, partitions, terrazzo floor, door sets, suspended ceilings, fixtures & fittings etc

  • Removal of external front facade panel windows & main entrance doors & alter to suit new entrance screen

  • Supply & fit steel support framework for new bronze anodised finish aluminium clad entrance to match existing exterior consiting of: automatic sliding doors, hinged pocket doors (disabled access) all to match existing entrance

  • Also supply & fit: new front elevation glazed panels with applied dot manifestation and internal glazed screen for controlled access

  • New reception/work station for two persons, installation of FF&E

  • New tiled floor, new suspended metal tile ceiling and re-positioned ducting for existing forced air ventilation system

  • Plaster, paint & decorate throughout to high standard